Page -12- Clarke
®
Operator's Manual -Fusion 27 Battery Burnisher
HOW TO OPERATE THE MACHINE
HOW TO PREPARE THE MACHINE FOR OPERATION
How To Install The Pad
To install the pad on the machine, follow this procedure:
1. Position the pad centered on the pad driver.
See figure 6
2. Install and tighten the pad retainer.
How To Remove The Pad
To remove the pad on the machine, follow this procedure:
1. Loosen and remove the pad retainer.
2. Pull the pad from the pad driver. See figure 7.
Retainer
Retainer
Pad Pressure Operation
In order to maintain the amount of "pad pressure" being
applied to the floor, this machine comes with:
1. Pad Presssure Meter - "10 Bar" LED, (2)
Yellow, (6) Green and (2) Red. This is located on
the upper right side of the control panel. See
figure 8.
2. 90 amp circuit breaker
3. Pad Pressure adjustment nut
The color bands on the pad pressure meter indicate
whether the pad pressure is too low (Yellow); within
recommended pad motor specifications (Green); or too
high (Red). If the machine is operating in the Red band
for more than 5 - 10 seconds, the circuit breaker will
"pop", indicating that the pressure on the floor has
exceeded the pad motor specifications. Excessive
"popping" (or blowing) of the circuit breaker will cause the
breaker to stop functioning and will need to be replaced.
This machine operates on a "Pivot-Control" system. This
allows for the machine to "float" along the floor consis-
tently and continues to burnish the floor as the pad
wears. When the pad pressure meter starts to operate in
the Yellow band, it is recommended that the pad be
checked for excessive wear and possible replacement.
If the machine operates in the (Red) band for more than 2-
3 seconds, it is recommended that you reduce the
amount of pad pressure being applied to the floor. Refer
to the "Pad Pressure Adjustment" instructions.
Figure #6
Figure #7
Figure #8
Pad Pressure
Meter
Yellow
Green
Red
Factory
Setting
Recommended
Setting
Vista de página 11